Project #2 - Cooling Tower Replacement
Project #2 - Cooling Tower Replacement
Scope of Work:
Client advised TurboChyll that the Fan Motor Shaft had final broke and it was time to replace the Cooling Tower entirely.
TurboChyll hired an Engineer and Structural Engineer to develop Drawings and Plans to provide the client a price on.
Once awarded the project, TurboChyll worked to Remove the Existing Cooling Tower and properly Dispose of.
Install New Steel according to Structural Engineers Drawings.
Furnish and Install / New Cooling Tower onto New Steel with New VFD’s, New Spring Isolators, New Electrical Panels, and New Chilled Water Piping/Insulation.
After Photos of New Tower Install – Including New Steel / Piping / VFD’s